Gas Inlet Pipework Installation – School

Project Overview

From 19th May to 27th May 2026, the Utilities Department delivered a gas inlet pipework upgrade. Martin Curry managed the project.

The team surveyed, designed, fabricated, and installed a new 4” gas inlet system. This work improved the existing setup and ensured compliance with current standards. The team completed the project within the client’s schedule and operational window.

Objectives

The team aimed to install a gas inlet system that improved safety, reliability, and access for maintenance.

They completed a detailed site survey and developed fabrication drawings. They installed a new inlet with cathodic protection and removed redundant pipework. The team also reconfigured the system by installing a new valve and relocating the governor to improve access.

Project Detail

The team began with a site survey to confirm measurements and define the pipe route. They produced spool drawings and issued them for fabrication. The fabrication team built all pipework in line with internal procedures and technical standards.

During installation, the team removed redundant pipework and set up the work area with correct isolations and supports. They installed the new pipework and added adjustable supports to maintain system integrity.

They wrapped the inlet and installed a cathodic protection point. The system was then positioned for connection to the PE roadside supply.

Inside the building, the team installed new pipework and a client-supplied valve. They relocated the existing governor to improve access for maintenance.

They secured all connections using grade 8.8 bolts. They used Neoprene gaskets below ground and non-asbestos fibre joints above ground. This ensured a strong and compliant installation.

The team worked within a confined space and routed pipework around existing services and structures. Careful planning and early excavation checks allowed them to avoid clashes and deliver the project safely and efficiently.

Posted in