We are lifting or cutting in position the old mild steel tanks, this is a six year project and number 2 of 12 tanks.
- Pipework 316L seamless schedule 40.
- 10% X-ray on all butt welds.
- Pipework 100% pressure tested.
- Full document package on completion.
- The plant is live and it is a ATEX site.